The Foundry Construction Timeline, May 2018

The Foundry Construction Timeline, May 2018

The Foundry project in Downtown Loveland is moving forward! Curious about when you can expect to see each piece of The Foundry come to completion? Keep reading!

Current Construction Timeline:
Public Parking Garage – July 2018
Patina Flats on Lincoln - August 2018
Patina Flats on Cleveland - Late September 2018
Public Plaza - Late September 2018
Theater - Spring 2019
Hotel – Spring 2019

Project Info:
Total Land Area - 3.9 Acres
Total Residential Units – 155
Total Commercial/Retail - 14,206 SF
Hotel - 108 Rooms
Movie Theater - 7 Screens\\625 Seats
Public Plaza - 35,000 SF
Public Parking - 460 Spaces